  When it was announced that R&M had won the contract to build the Giant Dam Project,some of its institutional shareholders contacted Richard Markovnikoff,the chairman. They wanted reassurance that the company had fully taken the environmental issues and other risks into account. One fund manager asked if Mr Markovnikoff could explain the sustainability implications of the project to assess whether R&M shares were still suitable for his environmentally sensitive clients. Mr Markovnikoff said,through the company‘s investor relations department, that he intended to give a statement at the next annual general meeting (AGM) that he hoped would address these environmental concerns. He would also,he said,make a statement on the importance of confidentiality in the financing of the early stage working capital needs.

  (a) Any large project such as the Giant Dam Project has a number of stakeholders.

  Required:

  (i) Define the terms ‘stakeholder’ and ‘stakeholder claim’, and identify from the case FOUR of R&M’s external stakeholders as it carries out the Giant Dam Project; (6 marks)

  (ii) Describe the claim of each of the four identified stakeholders. (4 marks)

  (b) Describe a framework to assess the risks to the progress of the Giant Dam Project. Your answer should include a diagram to represent the framework. (6 marks)

  (c) Using information from the case,assess THREE risks to the Giant Dam Project. (9 marks)

  (d) Prepare the statement for Mr Markovnikoff to read out at the AGM. The statement you construct should contain the following.

  (i) A definition and brief explanation of ‘sustainable development’; (3 marks)

  (ii) An evaluation of the environmental and sustainability implications of the Giant Dam Project; (8 marks)

  (iii) A statement on the importance of confidentiality in the financing of the early stage working capital needs and an explanation of how this conflicts with the duty of transparency in matters of corporate governance. (6 marks)

  Professional marks for layout, logical flow and persuasiveness of the statement. (4 marks)

  (e) Internal controls are very important in a complex civil engineering project such as the Giant Dam Project.

  Required:

  Describe the difficulties of maintaining sound internal controls in the Giant Dam Project created by working through sub-contractors. (4 marks)

  (50 marks)

本文糾錯】【告訴好友】【打印此文】【返回頂部
將考試網(wǎng)添加到收藏夾 | 每次上網(wǎng)自動訪問考試網(wǎng) | 復(fù)制本頁地址,傳給QQ/MSN上的好友 | 申請鏈接 TOP
關(guān)于本站  網(wǎng)站聲明  廣告服務(wù)  聯(lián)系方式  站內(nèi)導(dǎo)航
Copyright © 2006-2019 考試網(wǎng)(Examw.com) All Rights Reserved  營業(yè)執(zhí)照
吉安市| 汝州市| 罗山县| 德保县| 洛隆县| 天门市| 襄垣县| 张北县| 平江县| 介休市| 日照市| 泰州市| 金堂县| 赤水市| 本溪市| 宜川县| 双城市| 石泉县| 乌鲁木齐市| 桐柏县| 田林县| 三原县| 江城| 大化| 内江市| 嵊泗县| 桐庐县| 满城县| 通江县| 柘城县| 锡林郭勒盟| 乳源| 青田县| 清徐县| 安阳县| 平谷区| 泌阳县| 衡水市| 巴里| 舟山市| 上犹县|